|
Market Watch · Issue 6 · Tuesday 4 August 2026 Watts HappeningThe UK energy newsletter that doesn't work for the industry |
|||
|
The Spark The queue to connect to Britain's electricity grid holds 73 gigawatts of data centre demand across 315 projects. The country's actual demand peaks at around 45 gigawatts on a cold winter evening. So the data centres waiting in line have booked, on paper, more grid than Britain uses at full stretch. Ofgem's own view is that much of it will never be built. This week it proposed charging developers up to £712,500 per megawatt just to hold their place, refunded only once they actually connect. The bottleneck was never only the pylons. Some of it was paperwork nobody meant to honour. |
|||
|
This Week in Watts Britain's grid queue is booked solid. Ofgem thinks a lot of it is a bluff.On 29 July, Ofgem opened a consultation on a new charge aimed squarely at data centres. Any project above 40 megawatts would have to lodge a Data Centre Commitment Fee when it accepts a grid connection offer, set between £237,500 and £712,500 per megawatt, roughly 2.5% to 7.5% of the project's build cost. The money comes back when the site is energised and is forfeited if the developer walks away. Alongside it, projects would have to prove real progress to keep their place: financial capability, procurement of long-lead equipment, and a credible end user. The reason is the queue itself. Between November 2024 and June 2025, contracted demand waiting to connect rose from 41 gigawatts to 125. Data centres account for around 73 of that. Set against a national peak near 45 gigawatts, the arithmetic doesn't hold as physical demand. Ofgem's read is that a large share of these applications are places held by developers keeping their options open, and that they push viable projects back and distort where the networks think they need to build. This is the big commercial connections queue, not the process your home solar goes through. It reaches the reader anyway. If you are a developer, a landlord, or a business quoted a connection date in the 2030s and a heavy reinforcement bill for a rooftop array, a battery, an EV hub or a heat pump retrofit, this queue is a large part of why. And the cost of planning networks around demand that never arrives lands on everyone through network charges. Two cautions. This is a proposal, open until 16 September, not a rule. And while Ofgem's earlier reform on the generation side brought forward 7.8 gigawatts of projects by an average of six years, the same effect on the demand side is expected, not banked. Nobody's connection date has moved yet.
|
|||
|
The Bill Buster
|
|||
|
Watts on the Market
|
|||
|
Quick Watts
|
